TE1ACC002 cavity history Last updated: 2009-04-01
 
Date Activity Notes
  Order Link to Vendor data
  Niobium QA Link to ECS look for 4/1/2008 data
  Fabrication
2009-01-14 QA Inner surface inspection by Ge, Wu
2009-01-29 EP 112 micron Kelly, Gerbick, Bice, Wu
  60 soap US +  DI hand rinsing Bice
2009-01-30 HPR 60 minutes Bice, Olis
HPR 110 minutes Bice, Olis
2009-02-02 Final Assembly Bice
  Pumpdown Bice, Montiel, Rowe, Wu
2009-02-03 leak check Bice, Wu
2009-02-04 RF test Ozelis
2009-02-09 Back fill and disconnect  
2009-02-13 Ethanol rinsing 10min No US afterwards
HPR 110 minutes?  
2009-02-17 Final Assembly, pumpdown  
2009-02-18 Leak check passed  
Cavity hookup to test stand  
T-map installed  
2009-02-19 Dewar prefill  
2009-02-20 RF test 2 31.5 MV/m, strong q-slope, no x-ray
2009-03-03 120 C in-situ baking  
2009-03-17 RF test 3 37 MV/m, limited by quench
2009-03-31 RF test 4 34.6 MV/m, limited by quench