Chamber Drawing Status
P2 drawings were delivered by Vladislav. They do
not include the frames drawing at this moment since je didn't receive them
from Wisconsin.
Panel Order
Nelson reported on the visit to Plascore 2 weeks
ago. It was clear from the visit that Plascore doesn't have the QA tooling
necessary to insure the conformance of the panels to our specifications.
Fermilab agreed that we will provide them the appropriate tooling. It was
unclear if Plascore would do the measurements (for the increase in the
panel cost that they already communicated to us) or if Fermilab will send
people to Plascore to measure the panels (for a cost that appeared to be
lower). While we are working on the QA tooling, Plascore will concentrate
on their assembly tooling to improve the quality of the panels. Mike Niemerski
(the Plascore engineer that visited Fermilab last week) identified three
possible points of improvement:
Core cutting: They will use a 5 feet wide table that should provide full support for the cutting of our wider core panels and decrease the problem of "fatter edges".Plascore also notified us that their process to produce the core for the panels will change by November (good thing it isn't changing in the middle of our production ! ) and that should imply a cost decrease of 25% in the core (it was not clear what this meant for the finished panels cost).Presses: They could investigate the effect of their presses on the presence of the "bumps" in the present panels (see report below by G.A.).
Curing Temperature: Plascore could monitor the curing temperature for the panels and check its effect on the panel bowing.
Panels Measurements
Giorgio reported on some panels
measurements done at Fermilab. All the panels measured (5 in total) show
a large bow in the long side direction (12 feet). When the panels are placed
under gravity of a flat granite table, the "long-side" bow largely disappears.
Although a full engineering analysis is not yet existing, it is hoped that
this implies that in the final chamber assembly this bow will disappear
as well. In the short side direction there are 2 "ridges", running along
the direction of the panel, where the panels bow by as much as 30-40 mils.
These bows do not disappear under gravity. We do not know what happens
in the final chamber. These "ridges" are located where the Plascore press
feet are located, so they appear to be a manufacturing problem. Plascore
knows about them, and they will check their production procedures to try
to minimize the problem.
Oleg presented his measurements
on a dry run assembly of the P2 chamber. The chamber was assembled
in the horizontal position and he measured the sagitta between the chamber
face and a straight edge laying on the chamber edges. He found a ~70 mils
sagitta at the center and wide side of the chamber, which is clearly unacceptable.
Approximately 20-30 mils are due to the buttons, which appear to be systematicaly
smaller than the gap bars. This problem is easily solved. The remaining
~40 mils are unexplained for. Jay Hoffman (TD Materials Lab) presented
some disturbing results on stress measurements he has being doing. He showed
that applying a force of 15-20 lbs on a button produced a deflection (on
a 2X2 inches piece) of 4-6 mils. This effect could explain the remaining
sagging of the chambers.
MP9
Most of the tooling has been
moved to MP9 according to the plans put down during the previous meeting
(the winding machine is still waiting for the final commissioning, but
that is proceeding OK as of today, Sep. 4). The tooling is being reassembled
in MP9 according to the plan discussed below.
Plans for the P2 pre-production
Chamber
Giorgio presented detailed plans
to get from here to the L3 milestone of assemblying the P2 pre-production
chamber by November 16. All the participants received a list of the action
items to focus on, in order to be able to make the chamber. Roughly speaking,
we will spend the first half of September completing the tooling setup,
assemble the chamber between September 15 and October 20, and start testing
the chamber by the beginning of September. Yuri will present the plans
for the cosmic test setup, in order to be ready to test the chamber as
soon as it comes out of MP9.